Grey Critical Chain Project Scheduling Technique and Its Application

Peng GAO, Jun-wen FENG, Hua-ting WANG

Abstract



Based on the idea of Grey System and interval number coefficient notation, a Grey Critical Chain scheduling approach is studied. According to Grey system theory, the time of project or task completion can be considered as the object that extension is definite but intension is uncertain, which is coincident with the character of the project management. The Grey Critical Chain Scheduling Technique mainly aims at the single project time management, but the management idea can also be applied to the other knowledge areas of the project management. In this Technique, we improve the selection method of the buffer time in the Critical Chain, in order to obtain reasonable Feeding Buffer time and Project Buffer time. In this paper, we will use an example to discuss the Grey Critical Chain Scheduling Technique, compare Grey Critical Chain with Program Evaluation and Review Technique, Critical Chain and Fuzzy Critical Chain, analyze the advantages, disadvantages and applicable scope of their own.
Key words: Critical Chain, Grey System, Interval Number, Schedule Management, Project Management
Résumé: Sur la base de l’idée de Système Gris et la notation du coefficient de nombre d’intervalle, l’approche de pragrammtion d’une Chaîne Critique Grise est étudiée. Selon la théorie du Système Gris, le temps du projet ou de la tâche peut être considéré comme l’objet dont l’extention est définitive mais l’intention est incertaine, qui est conforme au caractère du management de projet. La Technique de Programmation de la Chaîne Critique Grise vise essentiellement le management du temps du projet simple, mais l’idée de management peut aussi être appliquée dans d’autres domaines du management de projet. Avec cette technique, nous améliorons la méthode de sélection du temps d’amortissement dans la Chaîne Critique afin d’obtenir le temps d’amortissement de l’alimentation raisonnable et le temps d’amortissement de projet. Dans l’article présent, nous allons utiliser un exemple pour discuter la Technique de Programmation de la Chaîne Critique Grise, comparer la Chaîne Critique Grise avec l’Evaluation du Programme et la Technique de révision, la Chaîne Critique et la Chaîne Critique Floue, et analyser leurs avantages, désavantages et champ d’application.
Mots-Clés: Chaîne Critique, Système Gris, nombre d’intervalle, management de programme, management de projet

Full Text:

PDF


DOI: http://dx.doi.org/10.3968/j.css.1923669720070303.005

Refbacks

  • There are currently no refbacks.


Copyright (c)



Reminder

  • How to do online submission to another Journal?
  • If you have already registered in Journal A, then how can you submit another article to Journal B? It takes two steps to make it happen:

1. Register yourself in Journal B as an Author

  • Find the journal you want to submit to in CATEGORIES, click on “VIEW JOURNAL”, “Online Submissions”, “GO TO LOGIN” and “Edit My Profile”. Check “Author” on the “Edit Profile” page, then “Save”.

2. Submission

Online Submissionhttp://cscanada.org/index.php/css/submission/wizard

  • Go to “User Home”, and click on “Author” under the name of Journal B. You may start a New Submission by clicking on “CLICK HERE”.
  • We only use four mailboxes as follows to deal with issues about paper acceptance, payment and submission of electronic versions of our journals to databases: [email protected]; [email protected]; [email protected]; [email protected]

 Articles published in Canadian Social Science are licensed under Creative Commons Attribution 4.0 (CC-BY).

 

Canadian Social Science Editorial Office

Address: 1020 Bouvier Street, Suite 400, Quebec City, Quebec, G2K 0K9, Canada.
Telephone: 1-514-558 6138 
Website: Http://www.cscanada.net; Http://www.cscanada.org 
E-mail:[email protected]; [email protected]

Copyright © Canadian Academy of Oriental and Occidental Culture